Frewin Road, Wandsworth, London SW18

Date Completed
2010
Designer
Room Below
Consulting Engineers
R.J. Groves Associates
Basement and fit out
Contractor
Room Below

Our clients are a professional couple with a young family needing more space. The property is a substantial mid-terraced house on ground and first floors and there is a second floor loft extension.

Construction of the substructure works took approximately sixteen weeks and fitting out a further ten weeks thereafter.

Our clients were heavily involved in the design of the fitting out works and they believe the basement has added £600,000 to the value of their home.